Clear Route Limited was engaged to carry out a full tunnel survey of two existing…
Nelson Street Feasibility Study
The scheme in the East London area involves critical new EHV electrical circuits necessary to ensure this area has constant and uninterrupted supply.
Solution
Clear Route involvement in this project commenced at the planning stage, where various route options were investigated via a desktop study and extensive route walks.
The results of this survey identified several areas where it was considered doubtful that the designed number and formation of ducts was able to be installed, which would effectively stop the whole project. Consequently, further investigations were undertaken. This survey, allied with further detailed discussions with relevant authorities, was then further extended to allow for a route to be utilised, satisfying both the technical needs of the installation and those of the relevant authorities.