Clear Route Limited was engaged to carry out a full tunnel survey of two existing…
Bathymetric Survey – Walthamstow Reservoirs
A new overflow structure is to be constructed across a common embankment between Walthamstow No.3 and No.5 Reservoirs.
Detail of the reservoir bed level in Walthamstow No.3 Reservoir is required.
Silt and bed levels were required on a 2 m x 2 m grid along the shoreline across the outlet from the proposed structure.
Solution
All survey level data related to the gauge board located on the outside of the valve shaft located in the south eastern corner of Reservoir No.5.
The gauge board depicts the Top Water Level.
GPS and Total station techniques were used to set out the grid, record levels and tie into the gauge board.