As part of the SSR4 upgrade scheme to the London Underground ABB appointed Clear Route…
Sutton Grange Biomass 33 kV Connection
Client
CG Power
Scope
- Connection of an Anaerobic Digester plant to the local Western Power Distribution (WPD) 33 KV network.
- Works were carried out by CRL as an Approved Lloyds Registered NERS Utility Connections Provider (UCP).
- Establishment of a new cable route between the Point of Connection (POC) and the Customers 33 KV switchgear.
- Cable installation , jointing and termination of cables to switchgear
- Testing of Power cables and earthing
- Handover procedure to Client for Adoption by WPD
- Electrical Senior Authorised Person (SAP)