Sutton Grange Biomass 33 KV Connection

Sutton Grange Biomass 33 kV Connection

Client

CG Power

Scope

  • Connection of an Anaerobic Digester plant to the local Western Power Distribution (WPD) 33 KV network.
  • Works were carried out by CRL as an Approved Lloyds Registered NERS Utility Connections Provider (UCP).
  • Establishment of a new cable route between the Point of Connection (POC) and the Customers 33 KV switchgear.
  • Cable installation , jointing and termination of cables to switchgear
  • Testing of Power cables and earthing
  • Handover procedure to Client for Adoption by WPD
  • Electrical Senior Authorised Person (SAP)